I spent a large part of the day fitting gravel boards and the frame for the new fence. Horizontal slats will be fitted eventually. It may take a while though as I need to paint them before I fit them and it’s too cold and wet to do that outside. I will miss the sheep…
Read MoreAuthor: Alvin Finn
Day 32 : Getting There
The groundworks are finally approaching their end. Today, the hardcore under the structural slab was flattened, the concrete pads for the steelwork finished and there was a bit of a tidy up.
Read MoreDay 31 : Bits & Pieces
Progress on various bits and pieces. The wet weather has not helped.
Read MoreDay 24 : Why No Posts?
It’s been a few days since I have posted, but things have been moving. Today, some more brick and blocks went in. Over the last few days, work has continued on the drainage. The rear soak away has been connected to the pipework for the ACO drain and guttering.
Read MoreDay 17 : Drains and Fences (again)
More work on the drains. Gravel boards installed on the fence posts. And BT have fixed the telephone line again.
Read MoreDay 16 : More Drains & Fence Posts
More work on the drains. Most of the new fence posts are in place and looking good.
Read MoreDay 15 : Drains
Second soak away installed (X marks the spot) and started connections for the drains.
Read MoreDay 11 : Blockwork & Fences
The blockwork went up today. It is amazing how quickly a good brickie can work. The rest of the old fence has gone and the holes dug for the new fence posts.
Read MoreDay 9 : Rain, rain, go away …
It’s raining. A lot. They’ve managed to mostly clear the ground ready for the slab and marked out for the blockwork. I am not sure if a lot else will get done today.
Read More